Proper installation and pre-use handling are the foundation of reliable fermentation performance. Following these critical steps helps prevent contamination, equipment damage, and process deviations.
1. Site & Utility Check
-Place the system on level ground; ensure good ventilation, cleanliness, and reliable grounding.
-Check power, instrument air, water, and steam pressure against your specific equipment specifications.
2. Unpacking & Assembly
-Verify all components against the packing list; inspect for transit damage.
-Secure all tank ports, bolts, and fittings to the recommended torque – do not overtighten manual valves.
-Ensure O-rings and gaskets are correctly seated.
▲Never start the agitator without water in the tank.
![]()
3. Sensor Calibration
-Calibrate pH and DO electrodes before sterilization.
-pH: Use two-point calibration with buffers matching your process. Rinse, do not wipe the electrode. Store in saturated KCl if not in use.
-Optical DO: No zero-point calibration needed. Calibrate 100% after sterilization, before inoculation, with max agitation and aeration.
▲ Protect the optical cap from organic solvents and strong oxidizers. Never add electrolyte.
4. Integrity Test
-Pressurize the assembled system with air; close all valves. Monitor pressure for ≥30 min.
-Detect leaks with soapy water; tighten or replace seals as needed.
▲ Must be completed before sterilization.
5. Water System Prime
-Open water injection and jacket valves; bleed until water flows without bubbles.
-Confirm circulation pump and jacket filling.
6. Air Compressor
-Drain condensate at least twice daily; check connections.
-Verify pressure switch and safety valve per compressor manual.
7. Cleaning & Sterilization Prep
-Clean tank with soft brush and purified water; drain completely.
-For SIP, ensure steam quality and do not introduce cooling water when tank temperature exceeds the specified limit.
-Keep all electrodes submerged; maintain exhaust valve open during sterilization.
8. Final Pre-Use Check
-After cooling, re-verify sensor readings.
-Disinfect connection points with 70% ethanol before aseptic connections.
-Run a water test to confirm agitation, temperature, and gas flow control.
▲ Key Safety
-Depressurize before servicing. Never create negative pressure during cooling.
-Keep air line pressure > tank pressure to prevent backflow.
![]()
ANTECH is an ISO9001: 2015 & ISO13485: 2016
quality management systems accredited company.
Corporate Office
Qingdao Antech Scientific Co., Ltd.
No. 182 Haier Road, Qingdao, China.
Reach our sales team
WhatsApp:+86 15806557756

Copyright © 2013 Qingdao Antech Scientific Co., Ltd. All Rights Reserved. Data Privacy Policy.
We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By clicking “Accept”, you consent to the use of ALL the cookies.